Project Management Professional (PMP) — Question 799
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue.
What should the project manager do lo encourage the team?
Answer options
- A. Schedule training courses to enhance team performance.
- B. Schedule working lunch meetings until the project is complete.
- C. Add new team members to help the project finalization.
- D. Initiate rewards and incentives according to assessment results.
Correct answer: D
Explanation
The correct answer is D because implementing rewards and incentives can boost team morale and motivation, especially during a stressful period. Options A and B do not address the immediate need for motivation, and option C may disrupt team dynamics rather than alleviate fatigue.