Project Management Professional (PMP) — Question 803
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected. What should the project manager do?
Answer options
- A. Perform a root cause analysis of the project performance.
- B. Adjust the original budget estimates with the current cost variance.
- C. Review the activity duration to reforecast the project completion date.
- D. Negotiate the project changes and adjust stakeholder expectations.
Correct answer: A
Explanation
The correct answer is A, as performing a root cause analysis will help identify the reasons behind the budget increase, allowing for informed decision-making. Options B and C focus on adjusting the budget or timeline without understanding the underlying issues, while option D involves negotiation without addressing the root causes of the budget shift.