An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer, C, emphasizes the importance of involving the operations team early in the planning and review stages, ensuring that support requirements are addressed in the backlog. Options A and D focus on external resources and documentation rather than direct collaboration with the operations team. Option B suggests a workshop but lacks the ongoing integration of the operations team in the project process.