Project Management Professional (PMP) — Question 750

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor is very keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

Answer options

Correct answer: A

Explanation

The correct answer is A because it emphasizes the importance of including the feature in the product backlog while also ensuring the sponsor understands the potential consequences of their request. Options B and D incorrectly suggest that the feature should be added to the iteration backlog, which could lead to team burnout and delays. Option C lacks the critical step of explaining the consequences to the sponsor, which is essential for managing stakeholder expectations.