Project Management Professional (PMP) — Question 735
A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.
What should the project manager do first?
Answer options
- A. Continue the project while trying to obtain the permit.
- B. Update the risk management plan.
- C. Review lessons learned from previous projects.
- D. Obtain the permits before continuing the build.
Correct answer: D
Explanation
The correct action is to obtain the permits before continuing the build (D) because proceeding without them incurs daily fines and may lead to legal issues. Continuing the project (A) is not advisable as it will result in penalties. Updating the risk management plan (B) and reviewing lessons learned (C) are important but should come after ensuring compliance with permits.