Project Management Professional (PMP) — Question 734

A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.

Which three actions should the project manager do? (Choose three.)

Answer options

Correct answer: A, C, D

Explanation

The correct actions involve identifying acceptance criteria and analyzing lessons learned to ensure quality standards are met (A, C, D). Option B is incorrect as acceptance criteria should be established during planning, not retrospectives. Option E, while important for project management, does not directly address ensuring quality measures are in place.