Project Management Professional (PMP) — Question 734
A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.
Which three actions should the project manager do? (Choose three.)
Answer options
- A. Identify in the iteration planning the acceptance criteria that meet quality standards.
- B. Identify the acceptance criteria during the retrospective that meet the quality standards.
- C. Analyze the lessons learned to determine appropriate testing metrics in quality standards.
- D. Incorporate performance metrics on the verified deliverables according to quality standards.
- E. Perform a risk analysis to determine the impact of not complying with quality standards.
Correct answer: A, C, D
Explanation
The correct actions involve identifying acceptance criteria and analyzing lessons learned to ensure quality standards are met (A, C, D). Option B is incorrect as acceptance criteria should be established during planning, not retrospectives. Option E, while important for project management, does not directly address ensuring quality measures are in place.