A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because adjusting the project plan allows for realistic timelines that consider the current team dynamics. Option A may not address the root cause of the delays, while B delays action that could exacerbate the problem. Option C could be premature if the project manager can resolve the issues at hand without escalating.