A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed.
What should the project manager do?
Answer options
- A. Request additional resources to be incorporated to the project team.
- B. Observe the project team and give them time to catch up before escalating.
- C. Escalate to the project sponsor and seek alternatives to resolve the issue.
- D. Review the issues and adjust the project plan to give a realistic schedule.
Correct answer: D
Explanation
The correct answer is D because adjusting the project plan allows for realistic timelines that consider the current team dynamics. Option A may not address the root cause of the delays, while B delays action that could exacerbate the problem. Option C could be premature if the project manager can resolve the issues at hand without escalating.