Project Management Professional (PMP) — Question 721

During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?

Answer options

Correct answer: B

Explanation

The correct answer is B because the project manager needs to address the issue immediately by updating the issue log, identifying stakeholders, and assigning resources to correct the problem. Option A is incorrect as changing quality requirements is not the first step in addressing a deliverable issue. Option C is not applicable since updating the risk register is not the immediate response needed for a specific deliverable issue. Option D does not focus on the immediate corrective actions required for the deliverable.