Project Management Professional (PMP) — Question 71

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer.
What guidance should the product manager provide to improve the requirement development?

Answer options

Correct answer: C

Explanation

Option C is correct because it encourages collaboration with the team to prioritize work that delivers value while still addressing the complex requirement. Option A is incorrect as it defers important work that could impact the project. Option B is not ideal because focusing solely on the complex work without considering backlog priorities may lead to inefficiencies. Option D is also wrong as it does not address customer expectations or the potential for incremental delivery.