Project Management Professional (PMP) — Question 687
Based on a new company policy, an aviation software project has been structured to use an agile approach. The project is subject to industry regulations, which require detailed tracking and archival of product changes.
What should the project manager use to understand the impact of compliance on this project?
Answer options
- A. User stories and release plan
- B. Product backlog and definition of done (DoD)
- C. Scope of work and product backlog
- D. Sprint retrospective and release plan
Correct answer: B
Explanation
The correct answer is B because the product backlog and the definition of done (DoD) help track requirements and ensure compliance with industry standards. User stories and release plans (A) focus more on user needs rather than compliance details. The scope of work and product backlog (C) do not specifically address the criteria for completion necessary for regulatory adherence. Sprint retrospectives and release plans (D) are reflective and planning tools, not primarily focused on compliance tracking.