Project Management Professional (PMP) — Question 688

A project manager is working on a project implementing a new time management system that will be rolled out in the next three months throughout the whole organization. Some managers have doubts about the transition period.

How should the project manager align with the managers during the rollout and cut over?

Answer options

Correct answer: C

Explanation

The correct answer is C because organizing sprint reviews based on the deployment schedule allows for targeted discussions and addresses specific concerns during the transition. Option A is too late in the timeline, while B might not effectively address all managers' needs, and D may not be practical for all senior managers to attend a single day event.