Project Management Professional (PMP) — Question 686
A development team member learned that one of the product features delivered in the last sprint would have greater business value if a small enhancement was made to the feature.
What should the project manager do next?
Answer options
- A. Conduct another sprint planning meeting and add the necessary story.
- B. Discuss this feature in the next sprint planning meeting.
- C. Discuss this feature during the upcoming retrospective meeting.
- D. Advise the team member to better prepare before sprint planning.
Correct answer: B
Explanation
The correct answer is B because discussing the feature in the next sprint planning meeting allows the team to assess its importance and prioritize it appropriately. Option A is not ideal as it suggests an unnecessary sprint planning meeting. Option C is incorrect because retrospective meetings focus on past sprints rather than planning future work. Option D doesn't address the enhancement's potential and shifts responsibility away from the planning process.