A company is set to execute a project across different localities and countries. Right before execution, a press release from one of the impacted communities expresses disapproval of the project.

What should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A because engaging critical stakeholders early helps to understand their concerns and align the project's goals with community expectations. Options B, C, and D are reactive measures that do not address the immediate need for stakeholder engagement and alignment.