Project Management Professional (PMP) — Question 655
A company is set to execute a project across different localities and countries. Right before execution, a press release from one of the impacted communities expresses disapproval of the project.
What should the project manager do first?
Answer options
- A. Engage all critical stakeholders and align project objectives with expectations from the community.
- B. Include the community statement as a new risk in the project’s risk register.
- C. Approach the government to obtain their support and influence to engage the community.
- D. Update the stakeholder communications plan to ensure that the community is always informed.
Correct answer: A
Explanation
The correct answer is A because engaging critical stakeholders early helps to understand their concerns and align the project's goals with community expectations. Options B, C, and D are reactive measures that do not address the immediate need for stakeholder engagement and alignment.