Project Management Professional (PMP) — Question 654

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

Answer options

Correct answer: B, C

Explanation

The correct answers, B and C, focus on equipping the team with the necessary understanding of agile practices and exploring alternative methodologies together, which can help ease the transition. Options A and E do not address the need for education or collaboration, and option D assumes the team is ready to manage agile processes without first understanding them.