Project Management Professional (PMP) — Question 653

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because ensuring that all stakeholders have access and know how to find project artifacts addresses the root cause of the problem. Option A does not directly resolve the stakeholders' issue, C shifts responsibility instead of providing a solution, and D is not sustainable as it does not improve access to future updates.