Project Management Professional (PMP) — Question 648

In a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because addressing potential impediments can help the team member overcome challenges and get the task back on track. Option A is not proactive as it merely informs rather than resolves issues. Option B removes responsibility from the team member without addressing the underlying problem. Option C may not be necessary if the real issue is a blockage that needs to be resolved.