Project Management Professional (PMP) — Question 646

A team member has encountered a technical issue, similar to the one faced in a successfully closed project. However, the team member did not know about the previous project and would like to resolve the issue on their own.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because sharing lessons learned helps the team member leverage previous experiences to resolve the current issue more efficiently. Options A and B do not directly provide the necessary knowledge from the past project. Option C, while beneficial for future projects, does not address the immediate need of the team member.