During the development of a new project’s definition, the project manager identifies that a similar project has recently been completed. What should the project manager do first?

Answer options

Correct answer: C

Explanation

The correct answer is C because reviewing lessons learned provides valuable insights and helps avoid past mistakes. While arranging knowledge-sharing sessions (A) and reviewing issue logs (D) can be useful later, they do not offer the immediate, focused insights that lessons learned do. Using the previous project's management plan (B) might not be applicable as each project can have unique requirements.