Project Management Professional (PMP) — Question 613
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
Answer options
- A. Reach an agreement with the team on how to handle the situation.
- B. Allow senior management to decide how to proceed with the project.
- C. Reach out to the procurement team to hire a substitute for the team member.
- D. Convince the team member not to leave until the project is completed.
Correct answer: A
Explanation
The correct answer is A because it emphasizes the importance of team collaboration and adaptability in agile practices. Allowing senior management to intervene or hiring a substitute may disrupt team dynamics and workflow, while convincing the team member not to leave is not a feasible or ethical solution.