Project Management Professional (PMP) — Question 610

Most of the work packages for a project are subcontracted. In the middle of execution, the project manager is informed that a new contract manager will take the position in one-week.

What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A, as understanding the new contract manager's interests is crucial for establishing a productive working relationship. Options B and C focus on administrative updates and meetings, which are less critical than directly addressing the new manager's interests. Option D, while thorough, may not prioritize immediate relationship management necessary for ongoing project success.