Project Management Professional (PMP) — Question 610
Most of the work packages for a project are subcontracted. In the middle of execution, the project manager is informed that a new contract manager will take the position in one-week.
What should the project manager do next?
Answer options
- A. Analyze and document the interests of the new contract manager and select a strategy to manage the relationship.
- B. Update the communications management plan with the new contract manager's information.
- C. Reschedule the next progress meeting to introduce the new contract manager to the project team.
- D. Consult the project management plan and prepare a full set of documents for the new contract manager.
Correct answer: A
Explanation
The correct answer is A, as understanding the new contract manager's interests is crucial for establishing a productive working relationship. Options B and C focus on administrative updates and meetings, which are less critical than directly addressing the new manager's interests. Option D, while thorough, may not prioritize immediate relationship management necessary for ongoing project success.