Project Management Professional (PMP) — Question 608

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because collaboratively creating the project management plans ensures that the team is aligned and has input on the project direction. Options A and B neglect the importance of having a structured plan, which is critical for project success. Option C, while potentially time-saving, may not address the unique requirements of the current project and could lead to inconsistencies.