Project Management Professional (PMP) — Question 607

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the Stakeholder Register is the document that should list all stakeholders involved in the project, including their roles in requirements collection. If the leader of the user party was not included in communications, it suggests that they were not documented as a stakeholder. The other documents, like the Risk Register, Project Charter, and Business Documentation, do not specifically pertain to stakeholder identification and engagement.