Project Management Professional (PMP) — Question 588
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
Answer options
- A. Continue project execution using the current blueprints from the client.
- B. Escalate this issue to the project sponsor.
- C. Consult with the client to determine if project execution should be continued.
- D. Reschedule the project execution date.
Correct answer: C
Explanation
The correct answer is C because consulting with the client is crucial to clarify any discrepancies before proceeding. Continuing with the current blueprints (A) could lead to further complications, escalating the issue to the project sponsor (B) may not address the immediate need for clarification, and rescheduling (D) does not resolve the issue with the blueprints.