Project Management Professional (PMP) — Question 589

Two functional managers disagree on key features of one deliverable during the planning of a project. The project manager discovers that each manager included requirements that contradict each other. The functional managers do not want to meet with each other to find a solution. This situation has been escalated to the sponsor who requests a meeting with them.
What strategy should the project manager use to resolve this conflict in the meeting?

Answer options

Correct answer: C

Explanation

The correct answer is C because it focuses on collaboration and understanding between the managers, which is essential for resolving conflicts. Answer A merely acknowledges the issue without seeking resolution, B limits options prematurely, and D could lead to further contention rather than a cooperative solution.