Project Management Professional (PMP) — Question 587
A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product.
Which approach should the project manager take?
Answer options
- A. Ask the team to raise blockers or impediments in daily meetings.
- B. Prioritize the tasks with high risks to reduce the number of iterations required.
- C. Ask the team to challenge the project estimations for a faster delivery.
- D. Prioritize deliverables based on business value and define frequent releases.
Correct answer: D
Explanation
The correct answer is D because prioritizing deliverables based on business value ensures that the most critical features are delivered first, allowing for frequent releases. Options A, B, and C do not directly address the need to reduce iterations or enhance delivery speed as effectively as prioritizing based on business value does.