Project Management Professional (PMP) — Question 587

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product.

Which approach should the project manager take?

Answer options

Correct answer: D

Explanation

The correct answer is D because prioritizing deliverables based on business value ensures that the most critical features are delivered first, allowing for frequent releases. Options A, B, and C do not directly address the need to reduce iterations or enhance delivery speed as effectively as prioritizing based on business value does.