Project Management Professional (PMP) — Question 562

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
What should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct action is to develop the resource management plan and ensure adequate training, as this addresses the skill gaps effectively and prepares the team for future tasks. Replacing team members (B) may not be feasible or necessary, outsourcing (C) could increase costs, and updating the issue log (D) does not provide a solution to the skill deficiency.