After a meeting with the customer, the project manager receives special recognition because the project is always on schedule. Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.
What should the project manager do in the project team meeting?
Answer options
- A. Share the customer feedback with the project team
- B. Follow the meeting agenda and make a list of the next deliverables
- C. Document this feedback in the meeting minutes
- D. Start planning how to improve the dates of next deliverables
Correct answer: A
Explanation
The correct answer is A because sharing customer feedback fosters transparency and motivates the team. Options B and C focus on administrative tasks rather than leveraging positive feedback, and D suggests a reactive approach to planning instead of celebrating successes.