Project Management Professional (PMP) — Question 561

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

Answer options

Correct answer: B

Explanation

The correct answer is B because using facilitation techniques allows the project manager to mediate the conflict and promote effective communication among all stakeholders, which can lead to a resolution. Option A does not address the conflict directly in the meeting, while options C and D unnecessarily postpone the meeting and could hinder progress.