Project Management Professional (PMP) — Question 560
A project manager prepared a project benefits management plan.
Which of the following should be included in this document?
Answer options
- A. Strategic alignment, benefits owner, risk register
- B. Target benefits, benefits owner, lessons learned
- C. Project requirements, target benefits, issue log, metrics
- D. Target benefits, strategic alignment, time frame for realizing benefits
Correct answer: D
Explanation
The correct answer, D, includes essential components such as target benefits, which define what the project aims to achieve, strategic alignment that ensures the project supports organizational goals, and the time frame for realizing benefits which is crucial for planning. The other options include elements that are either less relevant or do not comprehensively cover the necessary components for a benefits management plan.