Project Management Professional (PMP) — Question 554

A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.
Which project approach suits the scenario?

Answer options

Correct answer: A

Explanation

The Scrum approach is ideal for this scenario since it allows for flexibility and adaptability as requirements evolve. In contrast, a predictive project approach is rigid and not suited for changing requirements. Using the same method as the reference project may not account for the current project's unique needs, while stage gates could slow down the process rather than facilitate rapid adjustments.