Project Management Professional (PMP) — Question 553
A project team is completing a design, while another team in a different country is performing implementation.
How should the project manager communicate the design to the implementation team?
Answer options
- A. Upload the design documents into the project repository.
- B. Conduct a workshop with all of the stakeholders.
- C. Send a detailed email with the completed design document.
- D. Conduct a workshop with both of the teams.
Correct answer: D
Explanation
The correct answer is D because conducting a workshop with both teams allows for real-time communication and clarification of the design, ensuring that the implementation team fully understands the requirements. Options A and C lack interactive discussion, which can lead to misunderstandings, while option B does not involve the implementation team directly.