Project Management Professional (PMP) — Question 550

A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data. Some external stakeholders are reluctant to provide support.
What approach should the project manager take?

Answer options

Correct answer: B

Explanation

The correct answer is B because establishing dialogue with stakeholders helps clarify their concerns and fosters collaboration, which is crucial for project success. Option A may not address stakeholder issues directly, while C prematurely shuts down the project without exploring potential solutions. Option D focuses on internal processes but does not engage with stakeholders to mitigate risks.