Project Management Professional (PMP) — Question 549

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct action is to review the quality management plan, as it outlines the necessary standards and requirements, including regulatory labels. The other options, while potentially useful in other contexts, do not directly address the immediate issue of compliance with regulatory labeling.