Project Management Professional (PMP) — Question 548

A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.
What should the project manager do next?

Answer options

Correct answer: B

Explanation

The correct answer is B because evaluating the certification process allows the project manager to understand the potential timelines and prepare for any necessary adjustments. Options A and D suggest extending timelines without exploring current options, while option C might not be feasible or reliable without first assessing the certification process.