Project Management Professional (PMP) — Question 546

An organization has historically executed most projects using a predictive approach. The organization now wants to change over to an agile approach.
Which strategy will be useful to effectively help prepare the organization for this change?

Answer options

Correct answer: C

Explanation

The correct answer, C, emphasizes the importance of identifying and resolving obstacles that hinder the adoption of agile practices, thus improving the organization's readiness for change. Options A and B suggest adding layers of oversight or management, which can complicate the agile process rather than facilitate it. Option D's big bang approach can lead to chaos and resistance, making it a less effective strategy for such a cultural shift.