Project Management Professional (PMP) — Question 546
An organization has historically executed most projects using a predictive approach. The organization now wants to change over to an agile approach.
Which strategy will be useful to effectively help prepare the organization for this change?
Answer options
- A. Create a task force of executives who will monitor agile projects on a daily basis.
- B. Add multiple layers of managers who will be accountable for the agile execution.
- C. Improve organizational readiness by addressing impediments to agile in the organization.
- D. Take a big bang approach of moving the whole organization to agile at once.
Correct answer: C
Explanation
The correct answer, C, emphasizes the importance of identifying and resolving obstacles that hinder the adoption of agile practices, thus improving the organization's readiness for change. Options A and B suggest adding layers of oversight or management, which can complicate the agile process rather than facilitate it. Option D's big bang approach can lead to chaos and resistance, making it a less effective strategy for such a cultural shift.