Project Management Professional (PMP) — Question 540

During the design phase, a project manager realizes that the project will benefit from using adaptive tools. The effectiveness of this approach has been proven in past projects inside the organization.
What should the project manager do first?

Answer options

Correct answer: C

Explanation

The correct answer is C because assessing the team's capabilities ensures they are equipped to effectively use adaptive tools, which is crucial for successful implementation. Options A and B assume that the team is ready for adaptive tools without confirmation of their capabilities, while D suggests an unnecessary halt and additional costs, which is not an efficient approach.