A project manager is leading a project which shows a trend to exceed the cost baseline.
What should the project manager do first to manage the budget?
Answer options
- A. Ask the project sponsor for assistance in getting the budget back on track
- B. Meet with the project team to analyze the actual cost to determine deviations
- C. Inform the stakeholders that the project will be finished over budget
- D. Issue a change request including the analysis to increase the budget
Correct answer: B
Explanation
The correct answer is B because analyzing the actual costs with the project team allows the project manager to understand the reasons for the budget deviation before taking further action. Options A and D may be considered later, but they are premature without understanding the current financial situation. Option C does not address the management of the budget and only informs stakeholders of a negative outcome.