Project Management Professional (PMP) — Question 529
In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule.
What should the project manager do first?
Answer options
- A. Assign the tasks to another resource, and ask the resource to work double shifts
- B. Update the schedule to reflect the project's changes in duration
- C. Ask human resources (HR) for a replacement, and update the risk register
- D. Update the resource management plan and resource allocation chart accordingly
Correct answer: D
Explanation
The correct answer is D because updating the resource management plan and allocation chart enables the project manager to adjust for the resource's absence strategically. Option A is not ideal as it may overburden another resource, and options B and C do not address the immediate need for resource allocation adjustments.