Project Management Professional (PMP) — Question 510
An agile team is brainstorming end prioritizing all of the risks according to severity.
What should the teem do about the identified risks?
Answer options
- A. Mitigate the risks that are applicable to the current and following iterations.
- B. Focus on the project deliverables rather than the documented risks.
- C. Agree that any issue can be handled when it becomes a problem.
- D. Acknowledge that the risks will be handled in the corresponding iteration.
Correct answer: A
Explanation
The correct answer is A because it emphasizes the proactive approach of mitigating risks that could impact current and future iterations. Options B and C suggest neglecting risks or addressing them only reactively, which is not aligned with agile principles. Option D implies a passive acknowledgment rather than a proactive strategy for mitigation.