Project Management Professional (PMP) — Question 511

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined. The project manager is also informed that the key stakeholder does not want to hold a working session.
What should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A because sharing project documents allows the stakeholder to review and voice any concerns without forcing them into a meeting. Option B is less effective as it requires the stakeholder's participation, which they have already declined. Option C may create tension and is not a collaborative approach. Option D disregards the stakeholder's preferences and could lead to further misalignment in the project.