Project Management Professional (PMP) — Question 509
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?
Answer options
- A. Contact the vendor that supplied similar equipment for a previous project.
- B. Use the existing equipment and replace it later with the new equipment.
- C. Ask the project sponsor to expedite the vendor selection process.
- D. Work with the procurement team to find alternative options.
Correct answer: D
Explanation
The correct answer is D because working with the procurement team to identify alternative options can help mitigate delays in the approval process. Options A and B do not address the urgency of acquiring the necessary equipment, and option C, while potentially helpful, relies on the project sponsor's intervention rather than proactive problem-solving.