Project Management Professional (PMP) — Question 508

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task.
What should the project manager do to obtain the information required by the developer?

Answer options

Correct answer: D

Explanation

The correct answer is D because the product owner is responsible for defining and clarifying the acceptance criteria for tasks. The other options are not ideal as they either involve individuals who may not have the specific details needed (A, B, C) or may delay the clarification process.