Project Management Professional (PMP) — Question 507
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users' quality requirements.
What should the project lead recommend?
Answer options
- A. Develop a more comprehensive template for the definition of done (DoD).
- B. Establish a quality assurance (QA) team separate from the development team.
- C. Organize more frequent sprint reviews with a broader audience.
- D. Increase the percentage allocated for testing each backlog item.
Correct answer: A
Explanation
The correct answer, A, emphasizes the importance of a clear definition of done, which helps ensure quality standards are met consistently. Option B may create silos that hinder collaboration between teams, while C, although beneficial for feedback, does not directly address quality assurance. Option D increases testing resources but does not enhance the criteria for completion.