Project Management Professional (PMP) — Question 46

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline. There have been complaints from some stakeholders about some of the team members' performance. The project manager wants to understand the situation and provide feedback to the team as soon as possible.
What three actions should the project manager take to address this situation? (Choose three.)

Answer options

Correct answer: A, B, C

Explanation

The correct actions include defining team ground rules, which helps clarify expectations, performing a retrospective session to analyze past performance, and implementing daily team meetings for ongoing communication. The other options, such as requesting a manager performance review and conducting an annual review, are less immediate and do not directly address the current performance issues.