An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.
What key activity is needed to ensure the project's success?

Answer options

Correct answer: C

Explanation

The correct answer, C, emphasizes the importance of continuously monitoring the risk of the partner's system being unavailable and preparing resolution plans to address it if it occurs. This proactive approach helps to mitigate potential adverse effects on the project. The other options either do not adequately address the risk or suggest actions that could lead to miscommunication or dependency on the partner's system adjustment.