Project Management Professional (PMP) — Question 44

A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because holding a stakeholder meeting allows for clear communication and alignment on the new timeline and scope expectations. Options B, C, and D involve making significant changes to the project without first consulting the stakeholders, which could lead to misunderstandings and misalignment on project objectives.