Project Management Professional (PMP) — Question 43
A company wants to increase the commercial value of one of its products in a highly competitive market. In order to do this, the company commissions a project to create a prototype. The team constructs the prototype incrementally.
Which action should the project manager take as a priority?
Answer options
- A. Emphasize the use of Kanban methodology
- B. Ensure the project sponsor is aware of the go-to market date
- C. Deliver business value as soon as possible
- D. Implement a plan-do-check-act (PDCA) cycle
Correct answer: C
Explanation
The correct answer is C because delivering business value quickly allows the company to gain a competitive edge and respond to market demands sooner. Options A and D, while useful methodologies, do not directly address the urgency of delivering value. Option B, although important, focuses on communication rather than the immediate goal of adding value.