A company wants to increase the commercial value of one of its products in a highly competitive market. In order to do this, the company commissions a project to create a prototype. The team constructs the prototype incrementally.
Which action should the project manager take as a priority?

Answer options

Correct answer: C

Explanation

The correct answer is C because delivering business value quickly allows the company to gain a competitive edge and respond to market demands sooner. Options A and D, while useful methodologies, do not directly address the urgency of delivering value. Option B, although important, focuses on communication rather than the immediate goal of adding value.