Project Management Professional (PMP) — Question 424

A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market.

What should the project manager do to move forward with the project?

Answer options

Correct answer: B

Explanation

The correct answer is B because involving all stakeholders, including the farmers' group, is essential for ensuring that their needs and concerns are addressed, which can prevent conflicts later. Option A ignores the importance of stakeholder engagement, while C only documents a risk without taking action, and D shifts the responsibility of addressing the issue to the project sponsor rather than resolving it collaboratively.