Project Management Professional (PMP) — Question 425
During project implementation, one team finds out that a key project deliverable was not budgeted.
What should the project manager do first?
Answer options
- A. Escalate the issue to the project sponsor for resolution.
- B. Hold the team accountable and ask for an immediate solution.
- C. Meet with the team to discuss alternatives.
- D. Remove the deliverable from the project scope.
Correct answer: C
Explanation
The correct answer is C because the project manager should first engage with the team to evaluate possible alternatives before taking drastic measures. Options A, B, and D may not address the issue collaboratively or may lead to unnecessary escalation or removal of important project elements without exploring viable solutions.