Project Management Professional (PMP) — Question 421
A healthcare company is in the process of deploying an innovative healthcare solution globally. The project team has completed a limited release. The stakeholders have raised concerns about global healthcare guidelines and risks.
What should the project manager do next?
Answer options
- A. Evaluate lessons learned from similar projects prior to deployment.
- B. Perform a qualitative risk analysis on the identified project risks.
- C. Review compliance and regulatory requirements with stakeholders.
- D. Conduct a feasibility analysis of deploying the solution globally.
Correct answer: C
Explanation
The correct answer is C because reviewing compliance and regulatory requirements is essential to address the stakeholders' concerns about global guidelines and risks. Options A and B, while important, do not directly address the immediate compliance issues raised by stakeholders. Option D is also relevant but focuses more on feasibility rather than compliance.